Heating Infrastructure and Electrical Compliance Works
Weaverham High School
Client:
Sandstone Trust
Location:
Weaverham
Client:
Education
Client:
Building Services Engineering, Health & Safety, Project Management
Project Summary
Weaverham High School required a full upgrade of its heating and domestic water systems to improve efficiency, modernise performance, and prepare the infrastructure for future low-carbon heating technologies. The project involved complete replacement of the heating distribution network, domestic pipework, and heat emitters, designed around lower flow and return temperatures to enable future integration with air source heat pumps or other low-carbon systems. Following a detailed on-site electrical assessment, it was identified that a substantial portion of the existing electrical distribution infrastructure, was degraded, outdated, and non-compliant with current regulatory standards. To address these deficiencies, a comprehensive rewire and design of the system was undertaken.
Delivered from design through to as-installed completion, the project included a detailed thermal heat loss model using DesignBuilder to inform radiator schedules, zoning, and layout drawings. A comprehensive design including Amtech model and rewire was commissioned to ensure that all non-compliant electrical systems were renewed with appropriately selected equipment. Further to this new DFE compliant LED lighting and controls were designed and installed throughout to ensure lux level compliance as well as increase energy efficiency. The new scheme provided a modern, maintainable, and efficient system serving the 6,006 m² campus with minimal disruption to school operations.
Scope of Works
Strip out all existing mains heating distribution pipework and emitters.
Strip out of all non-compliant wiring, containment, submains and distribution equipment.
Install new heating distribution pipework from the plant room.
Installation of new wiring, containment, distribution boards and outlets.
Connect new systems to the boiler room infrastructure and update controls to reflect new zoning.
Boxing-in, replacing damaged ceilings, decoration, and making good of existing finishes.
Strip out all existing domestic hot and cold-water pipework.
Install new domestic hot and cold-water pipework from the plant room and insulate.
Installation of new zone controls and wiring for improved system monitoring and control.
A full schedule of testing and commissioning
Key Challenges and Design Approach
The existing underfloor routes required complete redesign, and coordination around structural steelwork demanded careful detailing. A comprehensive heat loss analysis informed emitter selection and zoning while a comprehensive Amtech model correctly sized and selected all required electrical equipment pipework and cable routes were optimised to minimise thermal losses and ensure limited disturbance to existing finishes.
Programme & Coordination
A detailed programme managed each stage from survey to completion, incorporating stakeholder engagement, design reviews, and value engineering. Coordination workshops were held fortnightly to resolve design queries and confirm constructability, guided by a Design Responsibility Matrix and Information Required Schedule to ensure quality and consistency.
Risk Management
E3C applied a systematic approach to identify and mitigate risks throughout delivery, reviewing high-risk areas and implementing practical control measures. This ensured continuity of school operations, programme adherence, and compliance with health, safety, and environmental standards.
Outcome
The new systems were completed on time and within budget, achieving significant improvements in comfort, controllability, and energy efficiency. The upgraded heating infrastructure provides Weaverham High School with a future-ready, low-carbon-compatible solution, with excellent client satisfaction upon handover.