MEP Heating Distribution & Rewire

St Margaret's

Client:
 

St Margaret's CofE Academy

Location:
 

Liverpool

Client:
 

Education

Client:
 

Building Services Engineering

Project Summary


Following an Electrical dilapidation report carried out at the site in early 2025, it was identified that much of the electrical distribution systems and associated submains were in poor condition, aged and non-compliant with modern regulations. Further to this, two proposed projects including a DFE expansion project and a Salix funded decarbonisation project would inevitably increase the electrical requirements on an already aged system.


Brief
E3Cube were appointed to design a new electrical distribution system that addressed the issues within the aforementioned dilapidation report while increasing the electrical capacity and physical space to accommodate the proposed projects. The project design encompassed the removal of an antiquated 400Amp busbar system and five associated switch boards to be consolidated within a single relocated 800Amp rated 3 phase 42-way Schneider switchboard with integral metering.


Output
All affected existing compliant wiring was identified and appropriate jointing and re-routing was designed and specified on appropriate containment systems to the new switch board location. All non-compliant cabling was redesigned to be replaced with appropriately sized cables protected by specified devices following the production of a comprehensive Amtech model. A local DNO (district network operator) isolation was sought to facilitate the relocation of the incoming supply with all DNO requirements included within the design pack.

The full RIBA stage 4 design pack was tendered to approved electrical contractors resulting in the appointment of a contractor to carry out the works. The electrical engineering department continued to support the project throughout the installation, visiting site to review progress and ensure strict adherence to the specification and design.  Before project close out and issue of practical completion a thorough Snagging was undertaken before installation test sheets were interrogated and counter signed for compliance.

E3 Cube Pattern_edited.png

Planning an similar project? Let’s talk it through.