A £4.1m redevelopment of one of Manchester’s largest primary schools — replacing a failing, asbestos-laden 1960s block with an efficient new teaching block, hall and entrance on a live site.

Chorlton Park Primary School

Client:
 

The Changing Lives in Collaboration Trust

Location:
 

Mancherster

Client:
 

Education

Client:
 

Architecture, Project Management, Cost Management

Project Overview

Chorlton Park Primary School is one of the largest primary schools in Manchester, serving children aged 3 to 11 years including nursery provision. The school originated with a detached Victorian building following by a second 1920’s building. There are also more recent extensions of various size, age and condition. The Trust initially appointed the services of E3 Cube to undertake a feasibility study investigating options to address a failing 1960s extension and part refurbishment of the 1920’s building. External improvements would create better outdoor recreation and teaching spaces whilst a reorganised car park would offer improved circulation and a safer new entrance area. 


Following confirmation of funding success, E3 Cube was appointed as lead consultant. E3 Cube undertook a spatial analysis of the entire campus, using Building Bulletin 103 (BB103), which enabled the accommodation within the 1960s block to be rationalised and reduced from 2,711m2  to 1,300m2  providing the School with significant occupational and energy efficiency savings.  


The following elements formed the final project scope: 

  • Removal of all asbestos-containing materials (ACMs) from within the 1960’s block 

  • Demolition of the entire 1960’s block at 2,711m2 

  • Construction of a replacement teaching block with new entrance and multi-purpose hall to be constructed as an extension to the existing building and designed to DFE Output Specification, Building Bulletins and Equality Act, etc

  • Internal alterations and classroom refurbishments. 

  • Reorganisation of car park and new main entrance area. 

  • Landscape improvements to create better outside spaces. 

The project was delivered in compliance with the DFE Output Specification and the exacting energy and sustainability requirements which satisfied Manchester City Council’s Planning Departments' sustainability standards. A stakeholder engagement strategy was devised in conjunction with the school to enable wider consultation on the emerging designs and their development. This strategy identified relevant project stakeholders such as the DfE, trustees, governors, staff, students, parents and the local community. Appropriate methods of communication were determined for each group including Stage Reports that were prepared at the end of each RIBA work stage to encapsulate all the key project decisions and actions.


A Master Programme was prepared which co-ordinated the Contractor's construction programme with the client's programme for ICT, furniture, relocations, etc. This timetable of planned activities identified critical events to avoid school disruption and reflect the site constraints. 


Areas of high risk, such as asbestos abatement on a live primary school site, were reviewed to ensure that all reasonably practicable measures were taken to mitigate them. Temporary classrooms were located in the school car park to enable students to be decanted from existing classrooms which in turn enabled internal refurbishments to take place. The construction programme was then sequenced in such a manner to enable the temporary classrooms to be vacated and removed allowing the reorganisation of the car park and entrance area.