Alsager School

Client:
 

Alsager Multi Academy Trust

Location:
 

Stoke-on-Trent

Client:
 

Education

Client:
 

Architecture, Project Management, Cost Management

Project Overview

Alsager School is a coeducational secondary school and sixth form with academy status. The school opened in 1955 and underwent major expansion in 1971. Alsager Leisure Centre was also constructed next to the school to create a wider cluster of education and community facilities. 


An increasing population within Alsager and the wider community was placing greater demand for school places at Alsager School. An expansion project was therefore planned with a brief to provide additional teaching accommodation for 30 extra pupils entering the school at Year 7. These annual increases would contribute to the organic growth of the enrolment from 1377 students to 1550. The new accommodation would include basic teaching, additional laboratories, a larger dining hall with a new catering kitchen and the refurbishment of sixth-form classrooms. 


Through the development of a campus master plan, we identified different locations for the new classroom block. Key considerations were the best use of under-used land, connectivity and student movements between the other school buildings and any other site constraints such as the presence of underground services. We also considered new build and extension alternatives for a new or expanded dining hall. 


Following extensive discussions with the school, the preferred option was agreed upon as follows: 

• A new build two-storey classroom building to become a dedicated sixth-form centre. 

• Refurbishment and extension of the existing school dining hall with new catering kitchen. 

• Reorganisation and refurbishment of the existing science labs to provide extra science lab spaces. 

• Refurbishment of the existing sixth-form classrooms to provide general classrooms.


Stakeholder Management 

The process began with a client team meeting (headteacher, bursar and facilities manager) to discuss the project requirements and a site walk round. Whilst the overarching project brief and funding allocation had been predetermined, this first meeting was pivotal in understanding the school’s exacting needs. 


During these discussions, it became apparaent that whilst the school was experiencing increasing demand for new students, they were also losing sixth-form students to a local sixth form college. The agreed solution was to propose a new sixth-form centre with its own identity and new facilities to help retain sixth-form students. The relocation of sixth-form students would in turn release existing classrooms to address the school’s expansion demands.


A broad range of potential options were formally presented to the School using tabulated data, drawings and images to aid understanding and the implications of each option. Each option was presented with supporting information including pros and cons, programme and indicative costs to facilitate informed decision making. 


Following determination of the agreed design solution, a schedule of regular progress review meetings were organised with the school. The purpose of these reviews was to report to key school representatives on matters such as design development, statutory approvals and programme. Stage reports were also prepared at the end of each RIBA work stage to encapsulate all the key project decisions and actions. 


A stakeholder engagement strategy was devised in conjunction with the school to enable wider consultation on the emerging designs and their development. This strategy identified relevant project stakeholders such as the DfE, trustees, governors, staff, students, parents and the local community with appropriate methods of communication established for each group. For example an open doors public engagement and information event was organised at the school to present the design proposals and obtain feedback. The same information was also uploaded to the school’s social media platforms with further opportunities to provide feedback. 


Liaison with the Planning Authority 

Early engagement with the planning authority was critical to a successful planning application. A preapplication planning enquiry was submitted to identify the principle of development would be acceptable. We were also advised that the early designs would be in-keeping with the other school buildings and to limit any new structures to the same height as the existing buildings. 


Open and transparent communication was maintained with the planning authority throughout the planning application process. For example, it was determined that extra bike storage should be provided to suit the school expansion and promote sustainable transport. New tree planting was also located along the site perimeter to offer privacy to a nearby graveyard. Creating a Design with Consideration for Multiple 


Construction Phases 

A three year development plan was devised to design, procure and sequence the construction work. This programme was dictated by three main construction areas: i) Science Labs; ii) Sixth-form block and dining hall; iii) Classroom refurbishment. Key considerations for any construction work within live school environments include any health and safety implications and minimising any disruption particularly during exam times. These constraints often influence the construction methodology, the sequencing of work and contractor selection. 


At Alsager School, the new sixth form centre and dining hall extension would be procured as a single project. Whilst these designs were being developed and statutory approvals obtained, the science lab programme was accelerated to ensure this work was undertaken in the school summer holidays to meet demand and minimise disruption to the school. A specialist contractor with experience of science lab refurbishment within tight timescales was appointed to complete this work ahead of the September re-start. 


A 12-month period was allocated to construct the sixth-form block and dining hall extension. Whilst the majority of construction work was undertaken within a self-contained construction site any sensitive operations or interfaces were agreed with the school and programmed to take place at suitable times. For example, any demolition and enabling works were sequenced to take place during school holidays with the catering kitchen refurb occurring during the summer holidays. 


The existing classroom refurbishment was deferred to the third year following movement of the sixth-form students into the new building. These small scale works were procured with a separate suitably sized contractor and undertaken during the summer holiday period to minimise disruption to the school.


Procurement 

Following an analysis of potential procurement options, a single-stage competitive tendering exercise was conducted in accordance with the Public Contract Regulations and the Trust’s Financial Regulations. Contractors were selected following a pre-qualification process. 


A robust set of tender documents were prepared including detailed drawings, specifications and schedules that were coordinated with all design disciplines. This approach offered greater cost certainty at tender stage and permitted effective cost management throughout the construction contract.